Diablo Canyon Decommissioning Engagement Panel

Public Comments

DateNovember 2, 2020
Decommissioning TopicWater Resources
Comment / Suggestion:

Written Comments, Questions and Answers received during the October 28, 2020 Online Engagement Panel Webinar Meeting:

Thanks for the follow-up on the breakwater question. Wouldn’t removal require its own round of permitting and CEQA assessment? I would think that is an off-ramp to this expensive and potentially disruptive effort.

Response 1 - Yes. However, previous state rulings offer that the temporary impacts can be outweighed by the long-term benefit from removal to restore habitat.

Support Information / Attachments